My Manufactured Home Guide

Electric hookup

Who hooks up power to a mobile home?

Three parties hook up power to a manufactured or mobile home: the power company brings service to the meter, a licensed electrician installs the meter base and the feeder to the home, and the county inspects before the meter is set.

Short answer: The electrician sets the meter base and disconnect — on a pole, a pedestal or the home — to the power company's specification, runs the feeder to the home's electrical panel, and bonds and grounds it. The power company connects its line to the meter base and sets the meter only after the inspections office passes the work. The home's panel and wiring came from the factory; the hookup is everything between the utility's line and that panel.

Reviewed by a manufactured home setup contractor and dealer.

Manufactured Home Land Check

Buying land for a mobile home? The Land Check reads the county's own permit rules for the one parcel you give us, and says where each answer came from and when.

$125. Asking takes no payment and places no order.

Check this land before you buy it

What to check first

Start with the exact property, quote, record, or job detail behind your question. Mark what is confirmed, what still needs a current source, and who must answer it. Use the checklist to keep the next call, document, or decision clear.

Manufactured-home service, feeder, disconnect, pedestal, grounding, connection, or circuit work when included.

Coordination with the serving utility, trench route, meter location, home installation instructions, and inspections.

Troubleshooting or correcting electrical items identified during setup or inspection.

Step 1

Home electrical specifications, installation manual, panel details, and dealer or installer scope.

Step 2

Utility provider, account or application status, service point, meter location, and required equipment.

Step 3

Site plan showing home, pedestal, trench, driveway, septic, well, and other utilities.

Details to Sort

The checks that usually matter before you commit money.

Meter base, pole or pedestal

The power company decides how service arrives — overhead to a pole or underground to a pedestal — and publishes the meter base specification the electrician has to follow. Call the power company early: the service application and the location of the meter base set the schedule for everything after.

The order of the hookup

Apply for service, have the electrician install the meter base and feeder, call for the electrical inspection, and the power company sets the meter. A temporary power pole for construction is a separate, earlier step if the trades need power before the home arrives.

Tell us the job and the ZIP. The request goes to the electrical category, where contractors who do this work see it.

Request a electrical hookup contractor

Secondary Support

Need more help understanding your situation?

Use the project router first, then share details for review if you still need help organizing the project context. This does not guarantee a provider match or availability.

Project Guide

Ask about electrical hookup

Share a few details to get an immediate starting point, likely next steps, useful guides, and relevant contractor categories. You do not need to know the exact permit or contractor type yet.

Add more project details (optional)

These details can help, but you can leave this closed if you are not sure yet.

Common questions

Does the setup contractor hook up the power?

Usually not. The setup contractor blocks, levels and anchors the home; a licensed electrician does the meter base and feeder, and the power company does the connection. Some turnkey contracts include the electrician.

What size service does a mobile home need?

The home's panel and data plate state the service it was built for; 200-amp is common on newer homes. The electrician sizes the meter base and feeder to the panel and the power company's specification.

Who pulls the electrical permit?

The licensed electrician, from the county inspections office. The meter is not set until the inspection passes.